- Whether the sheet metal installation is loose, whether the plastic plug is fully installed.
- Whether the sheet metal of die changing side is equal to the table panel height
- Whether the gap between electrical cabinet and sheet metal is even
- Whether the protective film of the grating cover is removed and whether the screws are missing
- Check whether the mold locating pin is installed
- Whether the flanges bearing on both sides of the platform panel is installed or not
- Check whether the positioning steel sleeve and copper sleeve of the machine slide plate are installed or loose
- LOGO configuration is printed according to the requirements
- Whether the screws at the servo structure are tightened
- Whether the screw at demoulding place is tight
- Whether the safety lock screw is tightened
- Whether the screws at the upper and lower clamping structure are tightened, and whether the signal is detected
- Whether the tightening height of the lower mold locking should be detected by the detection block
- Whether the column and upper and lower flange bolts are fastened
- Device warning signs installed
- Whether dust gun for equipment is installed
- Whether the access control switch is installed and fastened, whether the door is opened and closed smoothly, and whether the door lock flange screws are fastened